Friday, August 14, 2015

Aug 14 -Expenses Report

Total Expenses incurred from Aug 9 - Aug 14 2015 is P107,456.00  with details below:

Total House Project Expenses to DATE:, P 338,869.00
(since we started house construction)

Cash on Hand Available as of Aug 14 2015  is P 218,62500

Expenses Report from July 24 - Aug 8 2015 can be viewed here



Click the picture below to Enlarge and Zoom


Click the picture below to Enlarge and Zoom



Click the picture below to Enlarge and Zoom



Click the picture below to Enlarge and Zoom



Thursday, August 13, 2015

Hybrid Seedling 2: Replant after Storm Damage


Below is our "Pulling and Bundling" of Hybrid Seed Replanted to Fill the damaged and unfilled "6 kaloblob"  rice field which you can read in here which will be scheduled for transplant on August 15 2015.





Wednesday, August 12, 2015

2nd Floor: Cost of Tiles and Tile Works



Total Floor Area of 2nd Floor with concrete Slab is 85.5 Sqm

Polished Granite Tiles: Labor and Materials including adhesive cement and labor is estimated to be 

P750 (Labor and Materials) per sq meter x 82.5 sqm (2nd Floor)   = P61, 875.00


cost of 2 BathRoom Tiles @ P15,000 each                                                     =      30,000.00

including Walls 5 ft around each CR
                                                                      ==================
P 91,875.00  

All expenses will be accounted and reported to you      


     


Aug 11 - Progress Report