Nov 12- Progress Report

Laying Out the Common C.R. , Sink and counter on the 2nd Floor





Front Terrace Overview inside the second Floor - Irrigation and Ricefield visible






Bought Sink at Nothern tiles for P6,000 but haggled it to P5,300
Ditak mu choices Lababo keni - ala man apagpilian na mura. keng Dau, Mabalacat dakal sana pero sobra lawut nu karin ku sali.




Electrician working on the Stairway and in between Room Switches





Palitada works on the Front house and Back Terrace




Still working on the Master Bderoom C.R.